Release Cycle Tasks
This document describes the relative ordering and rough timeline for
all of the steps related to tasks that need to be completed during a
release cycle for Cinder.
Between Summit and Milestone-1
- Review output from the PTG and set Review-Priority on any high
priority items identified from those discussions. Send out recap to
the mailing list.
- Add any Cinder-specific schedule information to the release calendar
(https://review.openstack.org/#/c/509019/)
- Focus on spec reviews to get them approved and updated early in
the cycle to allow enough time for implementation.
- Review new driver submissions and give early feedback so there isn’t
a rush at the new driver deadline. Check for status of third party CI
and any missing steps they need to know about.
- Review community-wide goals and decide a plan or response to
them.
Milestone-1
- Propose library releases for os-brick or python-cinderclient if there
are merged commits ready to be released. Watch for any releases
proposed by the release team.
- Check progress on new drivers and specs and warn contributors if
it looks like they are at risk for making it in this cycle.
Between Milestone-1 and Milestone-2
- Review stable backports and release status.
- Watch for and respond to updates to new driver patches.
Milestone-2
- Propose library releases for os-brick or python-cinderclient if there
are merged commits ready to be released. Watch for any releases
proposed by the release team.
Between Milestone-2 and Milestone-3
- Review stable backports and release status.
- Set Review-Priority for any os-brick changes that are needed for
feature work to make sure they are ready by the library freeze prior
to Milestone-3.
- Make sure any new feature work that needs client changes are proposed
and on track to land before the client library freeze at Milestone-3. Ensure
microversion bumps are reflected in cinderclient/api_versions.py
MAX_VERSION.
- The week before Milestone-3, propose releases for unreleased changes
in os-brick. Include branch request for stable/$series creation.
Milestone-3
- Propose releases for unreleased changes in python-cinderclient and
python-brick-cinderclient-ext. Watch for releases proposed by the
release team. Include branch request for stable/$series creation.
- Set Review-Priority -1 for any feature work not complete in time for
inclusion in this cycle. Remind contributors that FFE will need to be
requested to still allow it in this cycle.
- Prepare “prelude” release notes as
summaries of the content of the release so that those are merged
before their first release candidate.
- Complete the responses to community-wide goals if not already done.
- Start assembling cycle-highlights for the team.
Between Milestone-3 and RC1
- Add cycle-highlights in the releases deliverable file.
RC1 week
- Propose RC1 release for cinder or watch for proposal from the release team.
Include stable/$series branching request with the release.
- Finalize any cycle-highlights for the release cycle.
- Remind contributors that
master
is now the next cycle but focus should
be on wrapping up the current cycle.
- Watch for translation and new stable branch patches and merge them quickly.
Between RC1 and Final
Propose additional RC releases as needed.
Note
Try to avoid creating more than 3 release candidates so we are not
creating candidates that consumers are then trained to ignore. Each
release candidate should be kept for at least 1 day, so if there is a
proposal to create RCx but clearly a reason to create another one,
delay RCX to include the additional patches.
Watch for translation patches and merge them quickly.
Make sure final RC request is done one week before the final release date.
Watch for the final release proposal from the release team to review and +1
so team approval is included in the metadata that goes onto the signed tag.
Final Release
- Start planning for next release cycle.
- Check for bugfixes that would be good to backport to older stable branches.
- Propose any bugfix releases for things that did not make the freeze for
final library or service releases.
Post-Final Release
- Make sure at least three SQLAlchemy-Migrate migrations are reserved
for potential backports (https://review.openstack.org/#/c/649436/).
- Unblock any new driver submission patches that missed the previous
release cycle’s deadline.
- Review approved cinder-specs that were merged to the previous cycle
folder that did not get implemented. Revert or move those specs to the
next cycles’s folder.